COUNTY

Boyle

ROUTE

CR 5230

DISTRICT 7-Lexington
ITEM NO 7-1113.00

PROJECT DESCRIPTION

Preliminary design and Final design for a bridge and approaches over North Rolling Fork River.

PROJECT MANAGER

I. J. Blankenship, P.E.

 

USER DIVISION

Highway Design

APPROXIMATE FEE $75,000, (Lump Sum)
PURPOSE AND NEED
Replace deficient structure.

PROJECT SCHEDULE & MILESTONES

 

RESPONSE DATE

May 3, 2005 4:30 P.M. (Frankfort Time)
 

SELECTION COMMITTEE DATE FIRST MEETING

May 17, 2005

  PRE-DESIGN CONFERENCE June 1, 2005
 

TENTATIVE DEADLINE FOR CONSULTANT FEE PROPOSAL

June 15, 2005

 

CONTRACT NEGOTIATIONS

June 29, 2005

  NOTICE TO PROCEED July 13, 2005
  PRELIMINARY LINE & GRADE November 1, 2005
  FINAL JOINT INSPECTION December 1, 2005
  RIGHT OF WAY PLANS February 1, 2006
  FINAL ROADWAY PLANS February 1, 2007
 
The selected consultant is expected to meet the scheduled milestone dates.
 
EVALUATION FACTORS
  1. Relative experience of consultant personnel assigned to project team with highway projects for KTC, and/or for federal, local or other state governmental agencies. (10 points)
  2. Capacity to comply with project schedule. (10 points)
  3. Past record of performance on project of similar type and complexity. (10 points)
  4. Project approach and proposed procedures to accomplish the services for the project. (10 points)
  5. Consultant's Kentucky offices where work is to be performed. (2 points)

 

75% - 100% of work accomplished in Kentucky offices – 2 points

26% - 74% of work accomplished in Kentucky offices – 1 point

0% - 25% of work accomplished in Kentucky office - 0 points

 

SELECTION COMMITTEE MEMBERS

  1. Joe Blankenship, User Division
  2. Ananias Calvin, User Division
  3. Chuck Allen, Secretary's Pool
  4. Katrina Bradley, Secretary's Pool
  5. John Slone, Governor's Pool

DBE REQUIREMENT

None

SPECIAL INSTRUCTIONS

The Department reserves the option to modify the selected consultant's agreement to include any necessary engineering and /or related services for this project. The firm(s) will at that time be prequalified by the Department in the required area(s).

SCOPE

The selected consultant will provide engineering services for Phase I and Phase II roadway design.

AVAILABLE KYTC STUDIES N/A
PROJECT LENGTH

.10 Miles

METHOD OF DESIGN

X CADD Capability (with DGN Intergraph Design File Format)

X Digital Terrain Modeling

 

ENVIRONMENTAL Department shall perform Service.
PHOTOGRAMMETRIC SERVICES Department shall perform Service.
STRUCTURE DESIGN
Consultant shall perform Service.
GEOTECHNICAL SERVICES

Department shall perform Service.

PROJECT FUNDING Federal Funds (BRZ)
TRAFFIC
Department shall perform Service.
PREQUALIFICATION REQUIREMENTS

The project team shall be prequalified in all areas as follows:

ROADWAY DESIGN

  • Rural Roadway Design <$250,000
  • Surveying

STRUCTURES

  • Spans under 500 feet
  • Culvert Design
MAP

CR 5230 Map