COUNTY |
Statewide |
|||
|
ROUTE |
N/A |
|||
| DISTRICT | Statewide | |||
| ITEM NO | N/A | |||
|
PROJECT DESCRIPTION |
To provide Fracture Critical Inspection of 13 Ohio River Bridges, In-depth Inspection of approximately 163 District 5 Bridges and Preparation of Repair Plans for 1 Kentucky River Bridge in Frankfort. Contract Package 1(Fracture Critical Inspection of 5 Ohio River Bridges and In-depth Inspection of approximately 39 District 5 Bridges):
Contract Package 2 (Fracture Critical Inspection of 3 Ohio River Bridges and In-depth Inspection of approximately 37 District 5 Bridges):
Contract Package 3 (Fracture Critical Inspection of 5 Ohio River Bridges):
Contract Package 4 (In-depth Inspection of Approximately 41 District 5 Bridges and Preparation of Repair Plans for 1 D-5 Bridge.)
Contract Package 5 (In-depth Inspection of Approximately 46 District 5 Bridges):
|
|||
| PROJECT MANAGER | Darrell K. Dudgeon, PE
|
|||
|
USER DIVISION |
Maintenance |
|||
| APPROXIMATE FEE | N/A | |||
| PURPOSE AND NEED | To
insure the structural integrity of these structure for their safe use
by the motoring public. |
|||
|
PROJECT SCHEDULE & MILESTONES |
RESPONSE DATE |
March 31, 2005 4:30 P.M. Frankfort Time | ||
|
SELECTION COMMITTEE DATE |
April 21, 2005 |
|||
| CONTRACT SCOPING MEETING | May 5, 2005 | |||
| NOTICE TO PROCEED | June 16, 2005 | |||
| COMPLETION OF INSPECTION SERVICES | December 31, 2005 | |||
|
COMPLETION OF PREPARATION OF REPAIR PLANS |
June 30, 2006 |
|||
The
selected consultant is expected to meet the scheduled milestone dates. |
||||
| EVALUATION
FACTORS |
75% - 100% of work accomplished in Kentucky offices – 2 points 26% - 74% of work accomplished in Kentucky offices – 1 point 0% - 25% of work accomplished in Kentucky office - 0 points |
|||
|
SELECTION COMMITTEE MEMBERS |
|
|||
|
DBE REQUIREMENT |
None | |||
|
SPECIAL INSTRUCTIONS |
The Department reserves the option to modify the selected consultant’s agreement to include any necessary engineering and/or related services for this project. If requested, the firm(s) must then be prequalified in the appropriate area(s).
|
|||
| SCOPE | Five consultants will be selected (1,2,3,4&5). The consultant ranked #1 will have first pick of the five packages, the consultant ranked #2 will have choice of the remaining four packages, and so on until all packages are taken. Consultant must be prepared to make selection at the time of notification of ranking by the selection committee. Inspection packages are randomly listed and do not necessarily reflect the order of importance or anticipated size of contract. |
|||
| AVAILABLE KYTC STUDIES | N/A | |||
| PROJECT FUNDING | State Funds | |||
| PREQUALIFICATION REQUIREMENTS | The firms must only be prequalified for the package they intend to select. They do not need to be prequalified for all packages and are to only select a package for which they have been prequalified. The bridge inspection packages requires prequalification in the area of Bridge Maintenance Services, In-depth Structure Inspection. The Preparation of Repair Plans Package (No.4) requires an additional prequalification for Structure Design - Spans Under 500'. The committee will not consider it an advantage to team up with other firms in order to prequalify for all packages.
|
|||