COUNTY |
Greenup |
|||
|
ROUTE |
KY 750 |
|||
| DISTRICT | 9-Flemingsburg | |||
| ITEM NO | 189.00 | |||
|
PROJECT DESCRIPTION |
Reconstruct KY 750 from US 23 to KY 3105 in Raceland. |
|||
| PROJECT MANAGER | Darrin Eldridge
|
|||
|
USER DIVISION |
Highway Design |
|||
| APPROXIMATE FEE | $225,000 | |||
| PURPOSE AND NEED | To
correct narrow lane widths to accommodate ingress and egrees of large
trucks and passenger cars. |
|||
|
PROJECT SCHEDULE & MILESTONES |
RESPONSE DATE |
March 29, 2005 4:30 P.M. Frankfort Time |
||
|
SELECTION COMMITTEE DATE FIRST MEETING |
April 20, 2005 |
|||
| PRE-DESIGN CONFERENCE | May 4, 2005 | |||
|
TENTATIVE DEADLINE FOR CONSULTANT FEE PROPOSAL |
May 18, 2005 |
|||
|
CONTRACT NEGOTIATIONS |
June 1, 2005 |
|||
| NOTICE TO PROCEED | June 15, 2005 | |||
| PRELIMINARY LINE & GRADE | January 15, 2006 | |||
| FINAL JOINT INSPECTION | October 15, 2006 | |||
| RIGHT OF WAY PLANS | February 15, 2006 | |||
| FINAL ROADWAY PLANS | August 15, 2006 | |||
The
selected consultant is expected to meet the scheduled milestone dates. |
||||
| EVALUATION
FACTORS |
75% - 100% of work accomplished in Kentucky offices – 2 points 26% - 74% of work accomplished in Kentucky offices – 1 point 0% - 25% of work accomplished in Kentucky office - 0 points |
|||
|
SELECTION COMMITTEE MEMBERS |
|
|||
|
DBE REQUIREMENT |
None | |||
|
SPECIAL INSTRUCTIONS |
The Department reserves the option to modify the selected consultant’s agreement to include any necessary engineering and/or related services for this project. The firm(s) will be asked at that time for prequalificans by the Department in the required area(s).
|
|||
| SCOPE | 1. Conduct preliminary engineering studies to identify appropriate typical section, line and grade, and dependable cost estimate. The environmental document at this time is expected to be a CE Level 1 which will be done by district. 2. The selected Consultant will be required to provide engineering services to perform Phase II roadway design, including the preparation of any design studies, drainage design, right of way plans, construction plans, traffic control plans and cost estimates.
|
|||
| AVAILABLE KYTC STUDIES | N/A | |||
| PROJECT LENGTH | 0.1 Miles |
|||
| METHOD OF DESIGN | X CADD Capability (with DGN Intergraph Design File Format) X CADD Based Automated Highway Design System X Digital Terrain Modeling
|
|||
| ENVIRONMENTAL | Department shall perform Service. | |||
| PHOTOGRAMMETRIC SERVICES | Department shall perform Service. | |||
| STRUCTURE DESIGN | The
selected consultant shall do the necessary engineering services to submit
to the Kentucky Transportation Cabinet an Advance Situation folder(s)
for the appropriate applicable structure(s). Upon submission of the folder(s),
a determination will be made whether the structure design will be performed
by the Department or by the consultant. Prequalification in the area of
structure design is required to be identified in the consultant's Response
to Announcement. |
|||
| GEOTECHNICAL SERVICES | Department shall perform Service. |
|||
| PROJECT FUNDING | Federal Funds | |||
| UTILITY DESIGN | The
selected consultant may be requested to provide utility related services
for this project, which may include construction inspection. |
|||
| TRAFFIC | Traffic
projections and related information will be provided by the Department. |
|||
| PREQUALIFICATION REQUIREMENTS | The project team shall be prequalified in all areas as follows:
|
|||
| MAP |
|
|||